Employer: OGDCL
Summary: The Project was High Priority and Emergency Situation due to Severe Gas Shortage in the Country. Therefore was completed to Make this Platform and Flood Protection Works on Fast-track Basis. The Area was Highly Risky due to involvement of SINDH Kachha Area. In order to Complete the Project with in stipulated Time Huge Resources were deployed I.E. 10 Excavators, 20 Tractors, 50 Dump Trucks, 1 Vibro Hammer ICE 1412C, 1 Concrete Batching Plant Etc.
Critical Quantities:
Excavation: 18 Million CFT
Embankment Filling: 90 Million CFT
Concrete: 0.5 Million CFT
Cofferdams: 35 Million CFT
Steel Sheet Piles: 5,500 Ton Steel Reinforcement: 1,000 Ton
Piling: 15,500 Ft