Employer: National Highway Authority
Summary: The Project is complete ahead of its schedule and bonus has been granted by NHA. The 1km long bridge is situated over river Chenab connecting district Muzzafargarah & district multan.it has 21 spans, each span is 41m long. There are total 82 girder, each having 150 ton weight. The girders were launched with company owned girder launcher.42no. Piles were executed in the river.
Critical Quantities:
Concrete -16674CUM
Steel – 2187 TON
Strand – 299 TON
Piles – 42 (60 METER DEEP)
Precast Girder – 84 no.